TERRA Engineering provided bridge inspections along Veterans Memorial Tollway in Illinois, including the structural inspection of 10 bridges and the lighting inspection of one. The bridge inspections involved the preparation of abbreviated bridge condition reports and cost estimates for each. Eight of the 10 bridges required repair drawings, additional cost estimates, and concept design reports. TERRA also prepared an abbreviated structure condition report for a culvert, an abbreviated noise wall condition report, four abbreviated sign structure condition reports, and lighting calculations. Spanning more than two years, the project cost $1.87 million.

Credits

TERRA was the prime for this job.